Dukesway Project – July 2016

Removal of slabs are now complete, crushed and stock piled on site, ready for our future use.

The strip foundations and pads to Unit 1 have all been poured with the steel bolt jigs and following the steel delivery, steel erection to Unit 1 will be starting 8th August 2016.

Unit 2 will be starting excavating the strips and pads this week, following on with concrete and bolt jigs.

Unit 3 has the formation level.

NPG are due to carry out The diversion works are due to be carried out by NPG this week.