Dukesway Project Progress
We are currently in week 30 of a 44 week project
Unit 1 has the concrete floors poured and sealed, the Mezz floor poured with the handrails fixed to the mezzanine. Blockwork is complete. Ist fix mechanical has started with 1st electrical starting tomorrow
Unit 2 has the blockwork and brickwork complete. 1st fix mechanical starting.
Unit 3 has steelwork erected.